UAA Sports Arena

196,000 sf multi-use facility that will house a 5,000 seat performance gymnasium for basketball & volleyball; a practice & performance gym for the gymnastics program; support space consisting of a fitness & training room, administration/coaching offices, laundry, A/V production, locker & team rooms for basketball, volleyball, gymnastics, skiing, track & cross country programs.

Project Cost

$109M

SCHEDULE
Partial Clearing & Working Pad: Nov 2011
Final Site Clearing: Mar 2012
Construction Begin Date: May 2012
Construction End Date: Jun 2014
Occupancy Date: Jul 2014

Updates
Board of Regents Update - Nov 2011
Community Council Update - Dec 2011